To keep you all abreast of developments, here is brief overview of the time line for the project.
Original Training:
October 22 & 23, 26 - 30
Gathering Material in Nairobi and receiving the team from America:
November 1-15
Installation of Solar Power at Emprukel:
November 16 - December 4
Commissioning of System at Emprukel:
December 5
Follow up training and completion of training:
December 6 - 12
At the end of all training two of our local technicians will be hired to
maintain the system. The trainee that shows the most enthusiasm and
aptitude will return to California next spring to take a nine month internship
at the Solar Living Institute in Northern California.
Currently it is Monday Morning in Kenya and we are preparing to start the
second week of training with our 20 trainees.